Data center restrictions tracker · Colorado

Data center moratoriums and restrictions in Colorado (2026)

Data snapshot 2026-08-15 · part of Pricing the Fear of Data Centers

As of August 15, 2026, this tracker documents 17 local government actions on data centers in Colorado, across 15 jurisdictions in 13 counties: 15 moratoria and 2 zoning exclusions. By status: 13 in force, 3 enacted, and 1 replaced.

There is no statewide restriction, incentive rollback, or large-load tariff on record for Colorado in this snapshot.

Data centers in Colorado used about 2.0 TWh of electricity in 2024; EPRI, Powering Intelligence 2026 (state-level dashboard) projects 2.7 TWh in its 2030, EPRI medium scenario.

Local actions in Colorado

Every documented local action in Colorado in the August 15, 2026 snapshot. Documented actions, not a census.
JurisdictionCountyActionStatusDate
MonumentEl Paso CountyMoratoriumin forceJuly 20, 2026
Woodland ParkTeller CountyMoratoriumin forceJuly 16, 2026
BroomfieldBroomfield CountyMoratoriumin forceJuly 7, 2026
Delta CountyDelta CountyMoratoriumin forceJuly 7, 2026
HudsonWeld CountyMoratoriumin forceJuly 1, 2026
South ForkRio Grande CountyMoratoriumin forceJune 18, 2026
Archuleta CountyArchuleta CountyMoratoriumin forceJune 16, 2026
Buena VistaChaffee CountyMoratoriumin forceJune 9, 2026
LongmontBoulder CountyMoratoriumenactedJune 9, 2026
Boulder CountyBoulder CountyMoratoriumin forceJune 2, 2026
Jefferson CountyJefferson CountyMoratoriumin forceMay 19, 2026
DenverDenver CountyMoratoriumin forceMay 18, 2026
Weld CountyWeld CountyZoning exclusionenactedApril 6, 2026
DenverDenver CountyMoratoriumin forceFebruary 24, 2026
Logan CountyLogan CountyZoning exclusionenactedFebruary 18, 2026
Larimer CountyLarimer CountyMoratoriumin forceJanuary 27, 2026
Logan CountyLogan CountyMoratoriumreplacedOctober 21, 2025

What one campus pays a local government

The parent piece's calculator puts a single large campus at $2M to $90M a year in local revenue, depending on the tax regime and abatements. The reference campus (Project Blue scale: $3.6B of capital, 286 MW) pays about $157M to local governments over 10 years. Permanent jobs run around 50 per facility.

Tax regimeReference caseAnnual local revenue, lowAnnual local revenue, high
Aggressive abatementMorrow County OR (enterprise zone)$2M$3M
Partial abatementGeorgia audit representative campus / El Paso Meta$27.8M$56M
Unabated equipment taxVirginia-style rates (Loudoun is the ceiling)$50M$90M

Run your own numbers in the calculator on the parent piece. Jurisdictions in Colorado that say no give up this revenue, not the jobs.

Sources

Back to Pricing the Fear of Data Centers