Data center restrictions tracker · Kansas

Data center moratoriums and restrictions in Kansas (2026)

Data snapshot 2026-08-15 · part of Pricing the Fear of Data Centers

As of August 15, 2026, this tracker documents 15 local government actions on data centers in Kansas, across 15 jurisdictions in 13 counties: 13 moratoria, 1 conditions ordinance, and 1 zoning exclusion. By status: 12 in force and 3 enacted.

There is no statewide restriction, incentive rollback, or large-load tariff on record for Kansas in this snapshot.

Data centers in Kansas used about 0.1 TWh of electricity in 2024; EPRI, Powering Intelligence 2026 (state-level dashboard) projects 0.4 TWh in its 2030, EPRI medium scenario.

Local actions in Kansas

Every documented local action in Kansas in the August 15, 2026 snapshot. Documented actions, not a census.
JurisdictionCountyActionStatusDate
City of EmporiaLyon CountyConditions ordinanceenactedJuly 23, 2026
Lyon CountyLyon CountyMoratoriumin forceJuly 23, 2026
Americus / Lyon CountyLyon CountyMoratoriumin forceJuly 15, 2026
City of LawrenceDouglas CountyMoratoriumenactedJuly 14, 2026
Geary CountyGeary CountyMoratoriumin forceJune 22, 2026
Bourbon County CommissionBourbon CountyMoratoriumenactedJune 15, 2026
Riley CountyRiley CountyMoratoriumin forceMay 18, 2026
Spring HillJohnson CountyZoning exclusionin forceMarch 25, 2026
Saline CountySaline CountyMoratoriumin forceMarch 17, 2026
Brown CountyBrown CountyMoratoriumin forceMarch 2, 2026
Marion CountyMarion CountyMoratoriumin forceMarch 2, 2026
Kingman CountyKingman CountyMoratoriumin forceFebruary 9, 2026
Sedgwick CountySedgwick CountyMoratoriumin forceJanuary 14, 2026
Harvey CountyHarvey CountyMoratoriumin forceJanuary 13, 2026
McPherson CountyMcPherson CountyMoratoriumin forceAugust 4, 2025

What one campus pays a local government

The parent piece's calculator puts a single large campus at $2M to $90M a year in local revenue, depending on the tax regime and abatements. The reference campus (Project Blue scale: $3.6B of capital, 286 MW) pays about $157M to local governments over 10 years. Permanent jobs run around 50 per facility.

Tax regimeReference caseAnnual local revenue, lowAnnual local revenue, high
Aggressive abatementMorrow County OR (enterprise zone)$2M$3M
Partial abatementGeorgia audit representative campus / El Paso Meta$27.8M$56M
Unabated equipment taxVirginia-style rates (Loudoun is the ceiling)$50M$90M

Run your own numbers in the calculator on the parent piece. Jurisdictions in Kansas that say no give up this revenue, not the jobs.