Data center restrictions tracker · Missouri

Data center moratoriums and restrictions in Missouri (2026)

Data snapshot 2026-08-15 · part of Pricing the Fear of Data Centers

As of August 15, 2026, this tracker documents 28 local government actions on data centers in Missouri, across 26 jurisdictions in 17 counties: 18 moratoria and 10 zoning exclusions. By status: 13 in force, 8 enacted, 5 pending, and 2 replaced.

At the state level, Evergy territory has a large-load tariff (enacted, November 13, 2025).

Data centers in Missouri used about 1.3 TWh of electricity in 2024; EPRI, Powering Intelligence 2026 (state-level dashboard) projects 3.6 TWh in its 2030, EPRI medium scenario.

Statewide actions in Missouri

  • Evergy territory: large-load tariff, enacted, November 13, 2025Large Load Power Service plan approved 4-0 (effective Dec 13, 2025) implementing SB 4: 75 MW+ eligibility, minimum monthly bill with an 80% demand-charge floor, 12-year minimum terms plus up to a 5-year ramp, exit charges and a cost stabilization rider. Docket MO PSC EO-2025-0154; minimum take 80%; term 12 yr. Source: Missouri PSC Report and Order, Case EO-2025-0154.

Local actions in Missouri

Every documented local action in Missouri in the August 15, 2026 snapshot. Documented actions, not a census.
JurisdictionCountyActionStatusDate
Nodaway CountyNodaway CountyMoratoriumin forceJuly 21, 2026
St. JosephBuchanan CountyMoratoriumin forceJuly 20, 2026
St. Charles CountySt. Charles CountyMoratoriumin forceJuly 13, 2026
NeoshoNewton CountyMoratoriumin forceJuly 7, 2026
IndependenceJackson CountyMoratoriumin forceJuly 6, 2026
SpringfieldGreene CountyMoratoriumin forceJune 29, 2026
Jackson CountyJackson CountyMoratoriumin forceJune 22, 2026
Jackson CountyJackson CountyMoratoriumenactedJune 22, 2026
Webster CountyWebster CountyMoratoriumin forceJune 16, 2026
Marion CountyMarion CountyMoratoriumin forceJune 15, 2026
City of St. LouisSt. Louis cityZoning exclusionpendingMay 19, 2026
St. CharlesSt. Charles CountyMoratoriumenactedMay 19, 2026
St. PetersSt. Charles CountyMoratoriumin forceMay 14, 2026
CamdentonCamden CountyMoratoriumin forceMay 5, 2026
Camdenton Board of AldermenCamden CountyMoratoriumenactedMay 5, 2026
ColumbiaBoone CountyMoratoriumin forceMay 2026
CentraliaBoone CountyZoning exclusionenactedApril 21, 2026
St. LouisSt. Louis cityMoratoriumenactedApril 21, 2026
BrentwoodSt. Louis CountyZoning exclusionpendingApril 6, 2026
City of LibertyClay CountyZoning exclusionenactedMarch 24, 2026
Franklin CountyFranklin CountyZoning exclusionpendingMarch 17, 2026
PacificFranklin CountyZoning exclusionpendingFebruary 25, 2026
WarrentonWarren CountyZoning exclusionenactedJanuary 20, 2026
Kansas CityJackson CountyZoning exclusionin forceJanuary 16, 2026
Villa RidgeFranklin CountyZoning exclusionpendingJanuary 15, 2026
Platte CountyPlatte CountyZoning exclusionenactedOctober 1, 2025
St. CharlesSt. Charles CountyMoratoriumreplacedAugust 22, 2025
PeculiarCass CountyMoratoriumreplacedAugust 19, 2024

Blocked or delayed projects in Missouri

From the outcome trace of large projects that hit a restriction: what happened next.
ProjectJurisdictionDeveloperOutcomeDecisionClaimed capex
Peculiar campus (Harper Road Technology Park)Peculiar (Cass County), MODiode VenturesdiedOctober 17, 2024$1.5B
Quality Hill downtown data centerKansas City, MORevitalization Unlimitedpending litigatingAugust 5, 2026
  • Peculiar campus (Harper Road Technology Park): Peculiar blocked Diode Ventures' $1.5B, 508-acre Harper Road Technology Park by deleting data centers from its zoning ordinance, effective Oct 17, 2024, after the 'Don't Dump Data in Peculiar' opposition campaign. No relocation of this specific project has been documented, though Diode continues separate Kansas City-area campuses it was already pursuing.
  • Quality Hill downtown data center: The City Plan Commission voted August 5, 2026 to deny the 20-story tower at 10th and Central after 475 opposition letters and none in support; the denial is a recommendation, and Miami-based Revitalization Unlimited can still ask City Council to override it. The developer has said only that it will take things one step at a time, and Mayor Lucas called a reversal highly unlikely.

What one campus pays a local government

The parent piece's calculator puts a single large campus at $2M to $90M a year in local revenue, depending on the tax regime and abatements. The reference campus (Project Blue scale: $3.6B of capital, 286 MW) pays about $157M to local governments over 10 years. Permanent jobs run around 50 per facility.

Tax regimeReference caseAnnual local revenue, lowAnnual local revenue, high
Aggressive abatementMorrow County OR (enterprise zone)$2M$3M
Partial abatementGeorgia audit representative campus / El Paso Meta$27.8M$56M
Unabated equipment taxVirginia-style rates (Loudoun is the ceiling)$50M$90M

Run your own numbers in the calculator on the parent piece. Jurisdictions in Missouri that say no give up this revenue, not the jobs.

Sources

Back to Pricing the Fear of Data Centers