Data center restrictions tracker · Nebraska

Data center moratoriums and restrictions in Nebraska (2026)

Data snapshot 2026-08-15 · part of Pricing the Fear of Data Centers

As of August 15, 2026, this tracker documents 8 local government actions on data centers in Nebraska, across 8 jurisdictions in 7 counties: 8 moratoria. By status: 4 in force, 2 enacted, 1 pending, and 1 replaced.

At the state level, the state has a ratepayer-protection law (enacted).

Data centers in Nebraska used about 4.8 TWh of electricity in 2024; EPRI, Powering Intelligence 2026 (state-level dashboard) projects 10.5 TWh in its 2030, EPRI medium scenario.

Statewide actions in Nebraska

Local actions in Nebraska

Every documented local action in Nebraska in the August 15, 2026 snapshot. Documented actions, not a census.
JurisdictionCountyActionStatusDate
Logan CountyLogan CountyMoratoriumin forceJuly 15, 2026
Broken BowCuster CountyMoratoriumenactedJuly 14, 2026
Cherry CountyCherry CountyMoratoriumin forceJuly 14, 2026
Cass CountyCass CountyMoratoriumpendingJuly 13, 2026
Seward CountySeward CountyMoratoriumin forceJune 30, 2026
Seward County Board of CommissionersSeward CountyMoratoriumenactedJune 25, 2026
Otoe CountyOtoe CountyMoratoriumin forceMay 19, 2026
Hitchcock CountyHitchcock CountyMoratoriumreplacedFebruary 3, 2025

What one campus pays a local government

The parent piece's calculator puts a single large campus at $2M to $90M a year in local revenue, depending on the tax regime and abatements. The reference campus (Project Blue scale: $3.6B of capital, 286 MW) pays about $157M to local governments over 10 years. Permanent jobs run around 50 per facility.

Tax regimeReference caseAnnual local revenue, lowAnnual local revenue, high
Aggressive abatementMorrow County OR (enterprise zone)$2M$3M
Partial abatementGeorgia audit representative campus / El Paso Meta$27.8M$56M
Unabated equipment taxVirginia-style rates (Loudoun is the ceiling)$50M$90M

Run your own numbers in the calculator on the parent piece. Jurisdictions in Nebraska that say no give up this revenue, not the jobs.