Augusta, Georgia: data center moratorium (2026)

Data snapshot 2026-08-15 · part of Pricing the Fear of Data Centers

Augusta, in Richmond County, Georgia, adopted a data-center moratorium on July 21, 2026. Its status in this snapshot is enacted.

The record reads: "Augusta (Richmond County) is moving toward a data center moratorium pending the development of new zoning rules. QTS has ongoing data center activity in the area, and officials are weighing a pause while standards are drafted. On June 2… (datacentertracker.org)."

Details

ActionClassStatusDateMW thresholdScopeSource
MoratoriumrestrictionenactedJuly 21, 2026not county-widedatacentertracker.org

Jurisdiction type: municipality. County: Richmond County. Dataset: datacentertracker. Snapshot August 15, 2026; documented actions, not a census.

Elsewhere in Richmond County

Georgia context

Georgia has 66 documented local actions across 60 jurisdictions in this snapshot. At the state level, the state has an incentive rollback (pending, February 12, 2026) and Georgia Power (PSC rule) territory has a large-load tariff (in force, February 1, 2025).

A town that says no to a data center gives up local tax revenue, not jobs: one large campus pays $2M to $90M a year depending on the tax regime, against roughly 50 permanent jobs. The parent piece prices it and lists the conditions that beat a ban.