Data center restrictions tracker · Indiana

LaPorte, Indiana: data center zoning exclusion (2026)

Data snapshot 2026-08-15 · part of Pricing the Fear of Data Centers

LaPorte, in LaPorte County, Indiana, adopted a data-center zoning exclusion on May 18, 2026. Its status in this snapshot is enacted.

The record reads: "The LaPorte Common Council weighed an annexation tied to a second Microsoft data center along Boyd Boulevard amid community opposition. The first Microsoft facility in LaPorte was a $1B, 245,000 sq ft project on 489 acres. UPDATE May 18… (datacentertracker.org)."

Details

ActionClassStatusDateMW thresholdScopeSource
Zoning exclusionrestrictionenactedMay 18, 2026not county-widedatacentertracker.org

Jurisdiction type: municipality. County: LaPorte County. Dataset: datacentertracker. Snapshot August 15, 2026; documented actions, not a census.

Indiana context

Indiana has 38 documented local actions across 34 jurisdictions in this snapshot. At the state level, the state has a tax action (enacted, March 12, 2026) and Indiana Michigan Power territory has a large-load tariff (in force, February 19, 2025).

A town that says no to a data center gives up local tax revenue, not jobs: one large campus pays $2M to $90M a year depending on the tax regime, against roughly 50 permanent jobs. The parent piece prices it and lists the conditions that beat a ban.

Sources