St. Joseph County Council, in St. Joseph County, Indiana, adopted a data-center zoning exclusion on May 13, 2026. Its status in this snapshot is pending.
The record reads: "A rezoning petition (~1,057 acres ag→industrial) for a THIRD New Carlisle-area data center (~$13B) had its first reading May 13, in the same cluster as the AWS Project Rainier (Anthropic) site. Opposition (Citizens for Responsible Economic… (datacentertracker.org)."
Details
| Action | Class | Status | Date | MW threshold | Scope | Source |
|---|---|---|---|---|---|---|
| Zoning exclusion | restriction | pending | May 13, 2026 | county-wide | datacentertracker.org |
Jurisdiction type: municipality. County: St. Joseph County. Dataset: datacentertracker. Snapshot August 15, 2026; documented actions, not a census.
Indiana context
Indiana has 38 documented local actions across 34 jurisdictions in this snapshot. At the state level, the state has a tax action (enacted, March 12, 2026) and Indiana Michigan Power territory has a large-load tariff (in force, February 19, 2025).
A town that says no to a data center gives up local tax revenue, not jobs: one large campus pays $2M to $90M a year depending on the tax regime, against roughly 50 permanent jobs. The parent piece prices it and lists the conditions that beat a ban.