Campbell County Board of Supervisors, in Campbell County, Virginia, adopted a data-center zoning exclusion on May 5, 2026. Its status in this snapshot is enacted.
The record reads: "Campbell County Board of Supervisors voted unanimously to require special use permits for all data centers, ending by-right development. Motion by Supervisor Matt Cline (Concord). Two existing pipeline projects grandfathered. (datacentertracker.org)."
Details
| Action | Class | Status | Date | MW threshold | Scope | Source |
|---|---|---|---|---|---|---|
| Zoning exclusion | restriction | enacted | May 5, 2026 | county-wide | datacentertracker.org |
Jurisdiction type: municipality. County: Campbell County. Dataset: datacentertracker. Snapshot August 15, 2026; documented actions, not a census.
Elsewhere in Campbell County
Virginia context
Virginia has 29 documented local actions across 27 jurisdictions in this snapshot. At the state level, the state has a tax action (enacted, June 30, 2026), the state has a ratepayer-protection law (enacted), Dominion Energy territory has a large-load tariff (enacted, July 31, 2026), and Dominion Energy (GS-5) territory has a large-load tariff (enacted, November 25, 2025).
A town that says no to a data center gives up local tax revenue, not jobs: one large campus pays $2M to $90M a year depending on the tax regime, against roughly 50 permanent jobs. The parent piece prices it and lists the conditions that beat a ban.