Fluvanna County, Virginia: data center moratorium (2025)

Data snapshot 2026-08-15 · part of Pricing the Fear of Data Centers

Fluvanna County, Virginia, adopted a data-center moratorium on November 19, 2025. Its status in this snapshot is enacted.

Fluvanna County, Virginia, adopted a data-center moratorium on September 17, 2025. Its status in this snapshot is replaced.

The records read: "Fluvanna County, Virginia, enacted a moratorium on data center development while studying zoning changes to address proposals spreading from Louisa and Albemarle counties. The Planning Commission voted 5-0 to strip data centers of by-right… (datacentertracker.org)." "Data-center moratorium running to a set end date, adopted 2025-09-17, since replaced by permanent regulations (Moratorium Nation)."

Details

ActionClassStatusDateMW thresholdScopeSource
MoratoriumrestrictionenactedNovember 19, 2025county-widedatacentertracker.org
MoratoriumrestrictionreplacedSeptember 17, 2025county-wideMoratorium Nation (ALEA Institute)

Jurisdiction type: county. County: Fluvanna County. Dataset: datacentertracker. Snapshot August 15, 2026; documented actions, not a census.

Virginia context

Virginia has 29 documented local actions across 27 jurisdictions in this snapshot. At the state level, the state has a tax action (enacted, June 30, 2026), the state has a ratepayer-protection law (enacted), Dominion Energy territory has a large-load tariff (enacted, July 31, 2026), and Dominion Energy (GS-5) territory has a large-load tariff (enacted, November 25, 2025).

A town that says no to a data center gives up local tax revenue, not jobs: one large campus pays $2M to $90M a year depending on the tax regime, against roughly 50 permanent jobs. The parent piece prices it and lists the conditions that beat a ban.