Cherokee County, Georgia, adopted a data-center moratorium on July 22, 2026. Its status in this snapshot is in force.
The record reads: "30-day data-center moratorium, adopted 2026-07-22, active per tracker (Moratorium Nation)."
Details
| Action | Class | Status | Date | MW threshold | Scope | Source |
|---|---|---|---|---|---|---|
| Moratorium | restriction | in force | July 22, 2026 | county-wide | Moratorium Nation (ALEA Institute) |
Jurisdiction type: county. County: Cherokee County. Dataset: moratorium nation. Snapshot August 15, 2026; documented actions, not a census.
Georgia context
Georgia has 66 documented local actions across 60 jurisdictions in this snapshot. At the state level, the state has an incentive rollback (pending, February 12, 2026) and Georgia Power (PSC rule) territory has a large-load tariff (in force, February 1, 2025).
A town that says no to a data center gives up local tax revenue, not jobs: one large campus pays $2M to $90M a year depending on the tax regime, against roughly 50 permanent jobs. The parent piece prices it and lists the conditions that beat a ban.