Data center restrictions tracker · Georgia

Polk County, Georgia: data center moratorium (2026)

Data snapshot 2026-08-15 · part of Pricing the Fear of Data Centers

Polk County, Georgia, adopted a data-center moratorium on March 3, 2026. Its status in this snapshot is replaced.

The record reads: "60-day data-center moratorium, adopted 2026-03-03, since replaced by permanent regulations (Moratorium Nation)."

Details

ActionClassStatusDateMW thresholdScopeSource
MoratoriumrestrictionreplacedMarch 3, 2026county-wideMoratorium Nation (ALEA Institute)

Jurisdiction type: county. County: Polk County. Dataset: moratorium nation. Snapshot August 15, 2026; documented actions, not a census.

Elsewhere in Polk County

Georgia context

Georgia has 66 documented local actions across 60 jurisdictions in this snapshot. At the state level, the state has an incentive rollback (pending, February 12, 2026) and Georgia Power (PSC rule) territory has a large-load tariff (in force, February 1, 2025).

A town that says no to a data center gives up local tax revenue, not jobs: one large campus pays $2M to $90M a year depending on the tax regime, against roughly 50 permanent jobs. The parent piece prices it and lists the conditions that beat a ban.

Sources

Back to Pricing the Fear of Data Centers